If Ram started his project on 24th Jan 2020 and completed it on last day of February the same year, then how many days did he take to finish it?
A
31
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
33
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
35
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
37
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is D 37 The number of days from 24th January to last day of February would be the sum of days left in January and the number of days in February.
2020 is a leap year. So, the month of February will have 29 days.
Number of days in each month would be: January = 8 days February = 29 days
So, the total number of days taken to complete the project is (8 +29) days = 37 days.