If the processes can take place simultaneously, what is the minimum time (In hours) required to get one unit of the final product?
___

Open in App
Solution

Processes P and R will be completed in 6 hours.

Then, processes Y and Q can be started simultaneously. Q will be completed at the end of 13 hours and Y at the end of 20 hours.

After process Q, S will get over at the end of 15 hours.

After process S, processes T, V and X can be started. Processes T, V and X will get over at the end of 19, 18 and 22 hours respectively.

Now, process U can be started immediately after 20 hours and it will get over in 10 more hours i.e., at the end of 30 hours.

Immediately process X gets over, i.e., after 22 hours, W can be started which will be completed at the end of 31 hours.

Thus, minimum time taken to complete one unit of the product is 30 hours.


flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Equations
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon