If the wages of 12 workers for 5 days are Rs.7500, find the wages of 17 workers for 6 days
Open in App
Solution
Wages of 12 workers for 5 days =7500=Rs.7500 Wages of 1 workers for 5 days =7500/12 =625 Wages of 1 workers for 1 day=625/5=125 Wages of 17workers for 1 days =125*17=2125 Rs Wages of 17workers for 6 days =2125*6=12750