In 25 days, one-fifth work is done by 10 men. If the number of days taken to complete three-fifth of the work is 75 days, then how many men were engaged?
Number of days | Amount of work done | Number of men |
25 | 15 | 10 |
75 | 35 | x |
25 : 75 = 1 : 3 | 15:35 | 10 : x |