In a barrage on pervious foundation, sheet piles are provided both upstream and downstream of the barrage to reduce uplift pressure and to prevent piping. Which one of the following statements is true in this regard?
A
Compared to downstream sheet pile, the upstream sheet pile is more effective in reducing uplift and piping
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
Compared to upstream sheet pile, the downstream sheet pile is more effective in reducing uplift and piping
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
Downstream sheet pile is more effective in reducing uplift while the upstream sheet pile is more effective in reducing piping
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
Upstream sheet pile is more effective in reducing uplift while the downstream sheet pile is more effective in reducing piping
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is D Upstream sheet pile is more effective in reducing uplift while the downstream sheet pile is more effective in reducing piping Upstream sheet pile
ϕC1=100−ϕE ϕD1=100−ϕD
Downstream sheet pile
ϕE=1ϕcos−1(γ−2γ)
ϕD=1ϕcos−1(γ−1γ)
Whereγ=1+√1+α22andα=bd
ϕD<50%
SoϕD1>50%forallvaluesofα
For normal range of 0.4<α<0.8
ϕE=50%
S0ϕC1=50%
Thus upstream piles are more effective in reducing uplift pressure. While down stream piles are more effective in reducing exit gradient.