In a blanking operation to produce steel washers, the maximum punch load used is 3×105N. The plate thickness is 5 mm and percentage penetration is 25. What is the work done during this shearing operation?

A
325 J
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
475 J
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
375 J
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
350 J
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 375 J
Work done=Fmax×pt
=300kN×0.25×5=375J

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Force and Workdone in Punching and Blanking
PRODUCTION
Watch in App
Join BYJU'S Learning Program
CrossIcon