Question

In a construction job, following are some probabilities given:
Probability that there will be strike is 0.65, probability that the job will be completed on time if there is no strike is 0.80, probability that the job will be completed on time if there is strike is 0.32. Determine probability that the construction job will get complete on time.

A
0.438
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
0.538
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
0.488
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
None of these
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 0.488
Let A be the event that the construction job is completed on time and B be the event that there is strike.

P(B)=0.65

Hence probability that there will be no strike =P(B)
=1P(B)
=10.65
=0.35

P(B)=0.35

By the Law of Total Probability we have P(A)=P(B)×P(A|B)+P(B)×P(A|B)

Given, P(constructionjobiscompletedwithnostrike)=P(A|B)=0.80
and P(constructionjobiscompletedwithstrike)=P(A|B)=0.32

P(A)=0.65×0.80+0.35×0.32=0.488

Hence the probability that the construction job will get complete on time is 0.488

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Total Probability Theorem
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon