Question

In a CPM network, a project activity has a normal cost with a normal duration of Rs 200 and 6 days. The same activity has a crash cost and crash duration of Rs 400 and 2 days. The crash cost slope of activity is

Open in App
Solution

Cost slope = CcCnTnTc

Cost slope = 40020062=2004=50