Question

In a hydropower station, a second reservoir is constructed near the region of water outflow ___


A

to control the flow of current as per the requirement of drinking water.

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

to control the flow of water as per our requirement of electricity.

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C

to keep the electricity generation constant.

No worries! We‘ve got your back. Try BYJU‘S free classes today!
D

when the demand for electricity is high, the water from the lower reservoir is pumped into the main reservoir.

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B

to control the flow of water as per our requirement of electricity.


In water storage plant, a second reservoir is constructed near the water outflow. When the demand for electricity is low, the surplus water is used to pump the water from the lower reservoir into the main reservoir. This is to ensure that a sufficient amount of water is available in the main reservoir to fulfil the peak loads i.e. when there is more demand of electricity.


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Hydroelectric power station
PHYSICS
Watch in App
Join BYJU'S Learning Program
CrossIcon