In a plane cement concrete pavement of thickness 20 cm, if the coefficient of friction is 1.4 and unit weight of cement concrete is 2400 kg/m3, allowable tensile stress is 1 kg/cm2 the spacing between the contraction joints is ___________m.

Open in App
Solution

Spacing between the contraction joints=2ScWf
=2×1×104(2400×1.4)=5.95 m
As per IRC maximum spacing is 4.5 m. Hence adopt spacing of 4.5 m .