wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

In a sand casting operation, the total liquid head is maintained constant such that it is equal to the mould height. The time taken to fill the mould with a top gate is tA. If the same mould is filled with a bottom gate, then the time taken is tB. Ignore the time required to fill the runner and frictional effects. Assume atmospheric pressure at the top of molten metal surfaces. The relation between tAandtB is

A

tB=2tA

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B

tB=2tA

No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

tB=tA2

No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
tB=22tA
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A

tB=2tA


Time taken to fill the mould with top gate

tA=AHAg2ghm ... (i)


Where,

A = Area of mould

H = Height of mould

Ag = Area of Gate

hm = Gate height

Given data:

hm=H, so Eq. (i) become:

tA=AhmAg2g .... (ii)

Time taken to fill the mould with bottom gate,

tB=2AAg2g(hmhmH)

tB=2AAg2ghm ... (iii)

From Eqs. (ii) and (iii), we get

tBtA=2

tB=2tA


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Aurangzeb
HISTORY
Watch in App
Join BYJU'S Learning Program
CrossIcon