In a sand casting process, a sprue of 10 mm base diameter and 250 mm height leads to a runner which fills a cubical mould cavity of 100 mm size.
The volume flow rate (in mm3/s) is
Vs=√2ghs=√2×9.81×250×103mm/s
Ac=π4×102=78.53mm2
Flow rate = VsAc=173942.13mm3/s