In arc welding of a butt joint, the welding space is to be selected such that highest cooling is achieved. Melting efficiency and heat trnas efficiency aare 0.5 and 0.7, respectively. The area of the weld cross section is 5mm2 and the energy required to melt the metal is 10J/mm. If the welding power is 2kW, the welding space in mm/s is closest to

A
4
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
24
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
14
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
34
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 14
Let the welding speed is Vmm//s

Volume of weld/sec =5Vmm3/s

(5V)×10=2000×0.5×0.7

V=70050=14mm/s

flag
Suggest Corrections
thumbs-up
2
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Early Conquests of Ranjit Singh
HISTORY
Watch in App
Join BYJU'S Learning Program
CrossIcon