In normal circumstances where ambient temperature does not fall below 15∘C, for a properly cured reinforced concrete slabs spanning up to 4.5 metre span cast using ordinary portland cement, the props provided can be removed only after a minimum period of
Type of Formwork | Formwork |
⋅ Props to slabs → Spanning up to 4.5m → Spanning over 4.5m |
7 days 14 days |
⋅ Props to beams and aches →Spanning up to 6m → Spanning over 6m |
14 days 21 days |
⋅ Vertical formwork to columns walls, beams. | 16−24 days |
⋅ Soffit formwork to slabs | 3 days |