Question

In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?

A
42
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
32
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
48
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
38
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 42
Less number of days then more number of people.
People and days are in inverse proportion.
Let x men are required to complete the job in 40 days.
as this is inverse proportion.
x:60::28:40

40x=60×28

x=60×2840

x=42

Hence, 42 men are required to complete the job in 40 days.

flag
Suggest Corrections
thumbs-up
2
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon