In the construction of networks, dummy activities are introduced in order to
A
Transfer resources, if necessary, during monitoring
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
Clearly designate a precedence relationship
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
Simplify the crashing plan
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
Compute the slack on all events
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B Clearly designate a precedence relationship Dummy Activity:
An activity which only shows the dependency of one activity over other, but doesn't consume any time or resources. Dummy activity is introduced to clearly designate a precedence relationship.