Question

It one machine would take 4 hours to complete a large production order and another machine 3 hours to complete the same order. How many hours would both machines take, working simultaneously at their respective constant rates, to complete the order?

A
712
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
112
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
157
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
312
No worries! We‘ve got your back. Try BYJU‘S free classes today!
E
7
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 157
Order completed by machine M1 in 1 hour =W4
Similarly, Order completed by machine M2 in 1 hour =W3

W4+W3=7W12

This means that when both machines are working together work done per hour
W127
So, the work will be completed in 127hrs
as
W127×127=W

Therefore Answer is 127hrs=157

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon