CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

It was estimated that 52 men can complete a strip in a newly constructed highway connecting cities P and Q in 10 days. Due to an emergency, 12 men were sent to another project. How many number of days, more than the original estimate, will be required to complete the strip?

A

3 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B

5 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

10 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D

13 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A
3 days
52 men can do in 10 days

Since 12 men were sent out

Remaining men left = 52 - 12 = 40

We know M1D1=M2D2

52×10=40×x

x=52×1040=13 days

Total number of days taken=13 days

3 days more than the original estimate.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time & Work
OTHER
Watch in App
Join BYJU'S Learning Program
CrossIcon