Question

Kamal can do a work in 15 days. Bimal is 50% more efficient than Kamal. What is the number of days, Bimal will take to do the same piece of work?

Open in App
Solution

If Kamal is 100% efficient then Bimal will be 150% efficient because it is given that Bimal is 50% more efficient than Kamal.

Now, lets find the ratio of the efficiency as follows:

BK=150100=32=3:2

Suppose Bimal takes x days to do the work, then we have:

3:2::15:x

32=15x

3x=15×2

3x=30

x=303

x=10

Hence, Bimal will take 10 days to do the same piece of work.