Question

Load frequency control is achieved by properly matching the individual machine's

A
reactive powers.
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
generated voltages.
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
turbine inputs.
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
turbine and generator ratings.
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C turbine inputs.
turbine inputs.