Question

M does 56th of the work in 25 days. He then calls in N and they together finish the remaining work in 4 days. How long would N alone take to do the whole work?


A

80 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

150 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

120 days

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D

100 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
E

None of these

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C

120 days


Whole work is done by M in (25 × 65) = 30 days

Now, (1 56) i.e., 16 work is done by M and N in 4 days

Whole work will be done by M and N in (4 × 6) = 24 days

M's 1 day's work = 130, (M+N)'s 1 day's work = 124

\therefore \!\, N's 1 day's work = (124 130) = 1120

So, N alone would do the work in 120 days.


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Speed-Distance-Time
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon