M does 56th of the work in 25 days. He then calls in N and they together finish the remaining work in 4 days. How long would N alone take to do the whole work?
120 days
Whole work is done by M in (25 × 65) = 30 days
Now, (1 − 56) i.e., 16 work is done by M and N in 4 days
Whole work will be done by M and N in (4 × 6) = 24 days
M's 1 day's work = 130, (M+N)'s 1 day's work = 124
N's 1 day's work = (124 − 130) = 1120
So, N alone would do the work in 120 days.