Match List-I (Description of activity floats) with List-II (Names of the floats) and select the correct answer using the codes given the lists:
List-I
A. Earliest start time of successor activity minus earliest activity in question minus the duration
B. Time available for an activity performance minus the duration of the activity
C. Excess of minimum available time over the required activity duration
D. Difference between total and free float of an activity
List-II
1. Total
2. Free
3. Interfering
4. Independent float
Codes:
A B C D