Question

Minimum centre to centre spacing of friction piles of diameter (D) as per BIS code is

A
1.5D
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
2D
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
2.5D
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
3D
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 3D
IS:2911 (Part-I)-1979 recommends a minimum spacing of 2.5 times the shaft diameter for point bearing piles, 3 times the shaft diameter for friction piles, whereas in loose sands or fill deposits, a minimum spacing of 2 times the diameter of the shaft is suggested. In the case of piles of non-circular cross-section, the diameter of the circumscribing circle shall be adopted.

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Pile in Sand- I
FOUNDATION ENGINEERING
Watch in App
Join BYJU'S Learning Program
CrossIcon