Mohan takes 9 hours to mow large lawn. He and Sohan together can mow it in 4 hours. How long will Sohan take to mow the lawn if he works alone? ​

Open in App
Solution

Step : Find the time taken by Sohan

Given:
Time taken by Mohan to mow the lawn =9 hours
Time taken by Mohan and Sohan to mow the lawn =4 hours

So,
Amount of work done by Mohan in 1 hour =19
Amount of work done by Mohan and Sohan in 1 hour =14

Amount of work done by Sohan in 1 hour =1419

=9436

=536

So, time taken by Sohan to mow the lawn =1536 hours

=365 hours

=715 hours