wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Mohit can complete a work in 50 days.wheraes Anuj can complete the same work in 40 days. Find : (i) work left after Mohit has worked on it for 20days.
​​​​​​ (ii) time taken by Anuj to complete the remaining work

Join BYJU'S Learning Program
CrossIcon