Activities A, B, C and D from the critical path for a project with a PERT network. The means and variances of the activity duration for each activity are given below. All activity durations follow the Gaussian (normal) distribution, and are independent of each other.
Activity A B C D
Mean (days) 6 11 8 15
Variance (days2) 4 9 4 9

The probability that the project will be completed within 40 days is ____. [Round off to two decimal places]

[Note: Probability is a number between 0 and 1]
  1. 50

Open in App
Solution

The correct option is A 50
PERT - CPM

TS=40 days, TE=6+11+8+15

TE=40 days,

2=TSTEσ=050%


Probability of completing project in expected time is always 50%.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Passage 10
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon