Question

Operating cycle can be delayed by ________________.

A
Increase in WIP period
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
Decrease in raw materials storage period
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
Decrease in credit payment period
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
Both (A) and (C) above
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
E
Both (B) and (C) above
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is D Both (A) and (C) above
Operating cycle period = Raw material storage period + Conversion period + Finished goods storage period + average collection period - average payment period.
An increase in WIP (or conversion) period will increase the operating cycle period and this will lead to a delay in the operating cycle.
Hence option (D) is the correct answer.

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Activity Ratios
ACCOUNTANCY
Watch in App
Join BYJU'S Learning Program
CrossIcon