Question

60 men can complete a work in 250 days. After 200 days, work is stopped for 10 days. How many additional men are required to finish it on time.

Open in App
Solution

60 men can finish a work with in 250 days.
1 man can finish the work in 250*60= 15000 days.

60 men worked for 200 days.
So the amount of work done is 200*60=12000 days
So the pending work = 15000-12000=3000 days
The work is stopped for 10 days.
The remaining number of days = 250-200-10=40 days.
The amount fo work done by 60 men in 40 days = 60*40=2400 days

Pending work = 3000-2400= 600 days.
Let x be the additional number of workers required.
Then 40x=600
x= 600/40=15

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon