P and Q take 6 hours and 8 hours respectively to complete a work. P works for 1 hour and then Q works for 2 hours. How much work is done in 3 hours?

A
512
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
127
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
125
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
712
No worries! We‘ve got your back. Try BYJU‘S free classes today!