P can do a job in 10 days, Q can do the same job in 12 days and R can do the same job in 15 days. In how many days they will finish the work together?
A
2
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
4
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
6
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
12
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A 4 Amount of work P can do in 1 day = 1/10 Amount of work Q can do in 1 day = 1/12 Amount of work R can do in 1 day = 1/15 Work done by P,Q and R in 1 day = 1/10 + 1/12 + 1/15 =15/60=1/4 Working together, they will complete the work in 4 days. Answer (B) 4