CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

P can paint a wall in 32 days and Q can do the same job in 24 days. With the help of R, they did the same job in 8 days only. Then, R alone can do the job in:


A

92/5 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

94/5 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

96/5 days

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D

20 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
E

None of these

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C

96/5 days


(P+Q+R)’s 1 day’s work =18

P’s 1 day’s work =132

Q’s 1 day’s work =124

R’s 1 day’s work = (18132+124)=596

So, R alone can do the work in 965 days.


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Geometric Applications of PNC
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon