P, Q and R can do a work in 12, 24 and 32 days respectively. They all begin together. P continues to work till it is finished. R left after 4 days and Q, one and half day before its completion. In what time is the work finished?


A

10.5 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

7.5 days

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C

9 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
D

12 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
E

None of these

No worries! We‘ve got your back. Try BYJU‘S free classes today!