P, Q, R and S are working on a project. Q can finish the task in 25 days, working along for 12 hours a day. R can finish the task in 50 days, working alone for 12 hours per day. Q worked 12 hours a day but took sick leave in the beginning for two days, R worked 18 hours a day on all days. What is the ratio of work done by Q and R after 7 days from the start of the project?
(60300=15)
While R worked for all 7 days @ 18 hrs/day
So he will do 18×7 = 126 of his work (Total work for 600hrs)
He will do(126600)=(0.21) of his work
So required ratio 15:126600
120:126
20:21