wiz-icon
MyQuestionIcon
MyQuestionIcon
9
You visited us 9 times! Enjoying our articles? Unlock Full Access!
Question

P, Q, R and S are working on a project. Q can finish the task in 25 days, working along for 12 hours a day. R can finish the task in 50 days, working alone for 12 hours per day. Q worked 12 hours a day but took sick leave in the beginning for two days, R worked 18 hours a day on all days. What is the ratio of work done by Q and R after 7 days from the start of the project?

A

10 : 11
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

11 : 10
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

20 : 21
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D

21 : 20
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C
20 : 21
Q can do work in 25×12=300 hrs

R can do work in 50×12=600 hrs

So we can say Q is twice efficient as R

Now Q worked only for 5 days @ 12 hrs/day.

So he will do 60 units of his work (Total work for Q i.e 300hrs)

he will do only 15 of work

(60300=15)

While R worked for all 7 days @ 18 hrs/day

So he will do 18×7 = 126 of his work (Total work for 600hrs)

He will do(126600)=(0.21) of his work

So required ratio 15:126600

120:126

20:21


flag
Suggest Corrections
thumbs-up
3
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time & Work
OTHER
Watch in App
Join BYJU'S Learning Program
CrossIcon