pavan can do a piece of work in 15 days. talbir can do the same work in 20 days, and Shyam can do it in 12 days.if all three work together, in how many days can they finish the job?
Open in App
Solution
Pavan can do the work in 15 days.
Talbir can do it in 20 days.
Shyam can do it in 12 days.
Therefore, their 1 day's work = 115+120+112=1260=15
Therefore, together they can finish the job in 5 days.