Question

PERT calculations yield a project length of 70 weeks with a variance of 9 weeks. The number of weeks required to complete the project with a probability of 95 % (probability factor for 95 %= 1.647) is _______

A
76.94 weeks
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
75.94 weeks
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
74.94 weeks
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
73.94 weeks
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 74.94 weeks
Std. deviation

=Variance=9=3

1.647=T703

T=74.941 weeks

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon