CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Pintu Takes 6 days more than those of Nishu to Complete Certain Work. If They Work Together They Finish it in 4 Days. How Many Days Would it Take to Complete the Work if they Work Alone.

Open in App
Solution

Let the number of days taken by Nishu be x
So,Number of days taken by Pintu will be x+6
Nishu's 1 day work=1x
Pintu's 1 day work=1x+6
Work done together in 4 days=14
1x+1x+6=14
x+6+xx2+6x=14
8x+24=x2+6x
x2+6x8x24=0
x22x24=0
x26x+4x24=0
x(x6)+4(x6)=0
x=4,6
Number of days cannot be negative.So,x=6
Thus, number of days taken by Nishu=6 and that of Pintu=6+6=12

flag
Suggest Corrections
thumbs-up
3
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon