Question

Pranab is thrice as efficient as Ghulam, and Ghulam is twice as efficient as Krishna. If the trio work together, how long will they take to complete a job which Ghulam completes in 25 days.

A
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A

Let total work be 100 units.

Ghulam’s one day work = 10025 = 4 units.

Pranab’s one day work = 12 units.

Krishna’s one day work = 2 units.

Combined work of the trio = 4 + 12 + 2 = 18 units.

Hence, They will take 10018=509 days. Option(a).

2nd method:- In place of unit, we can take in percentage form also.In one day, G=4% , P=12% , K=2%

Total in one day= 18% , Then 100% in 1008 days i.e 509 days. Option(a).


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Speed-Distance-Time
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon