Q20) A contract on construction job specifies a penalty for delay in completion of the work beyond acertain date is as follows: Rs. 200 for the first day, Rs.250 for the second day, Rs. 300 for the thirdday etc., the penalty for each succeeding day being 50 more than that of the preceding day. How much penalty should the contractor pay if he delays the work by 10 days?