Q43.A, B and C can do a piece of work in 11 days, 20 days and 55 days, respectively, working alone. How soon can the work be done if A is assisted by B and C on alternate days?
(b) 8 days
Work done by A in one day = 111
Work done by B in one day = 120
Work done by C in one day = 155
Work done by (A + B) in one day = 111+120=31220
Work done by (A + C) in one day = 120+155=655
Work done by (2A + B +C) in 2 days
=31220+655=55220=14
Work done by (2A + B + C) in 1 day = 18
So, work will be completed in 8 days