CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
228
You visited us 228 times! Enjoying our articles? Unlock Full Access!
Question

Rahul can do 12 of a piece of work in 6 days ,while Rohit can do 14 of the same work in 2 days . in how many days can both do it together?

A
6
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
5
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
4
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
7
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 6
We should use rate=worktime

Rahul's rate =(12)6=112

Rohit's rate =(14)2=18

Now, combined rate of Rahul and Rohit is 112+18

=224+324=524

How many days does it take them, working together, to finish the job?
Work=1
When work is 1, rate and time are inversely proportional (OR)
time=1rate

time=1(524)

time=245=445 days

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Simple and Compound Interest
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon