Ram can complete the work in 10 hours, Ajit in 12 hours and Suresh in 15 hours. All of them began the work together, but Ram had to leave the work after 2 hours of the start and Ajit left 3 hours before the completion of the work. How long did the work last.

A
8 hrs
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
7 hrs
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
9 hrs
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
8.5 hrs
No worries! We‘ve got your back. Try BYJU‘S free classes today!
E
can’t be determined
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 7 hrs

Soln: Option (b)

In 1 hour Ram can do 10% of the work, Ajit can do 10012% of the work and Suresh can do 10015% of the work.

So, total number of hours = 2 + 2 + 3 = 7 hours. Hence option (b)


flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Speed-Distance-Time
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon