Ram can do a piece of work in 6 days and Shyam can finish the same work in 12 days. How much work will be finished if both work together for 2 days?
A
One-fourth of the work
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
One-third of the work
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
Half of the work
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
Whole of the work
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A Half of the work Ram's 1 day's work =16 Shyam's 1 day's work =112 The part of work in 2 day's by both =2(16+112)=2(2+112)=2×312=12