Ramesh does 110th of work in an hour while his friend does 110000th of what Ramesh does in the given time. What part of work did Ramesh's friend complete in an hour ? [2 MARKS]

Open in App
Solution

Steps: 1 Mark
Answer: 1 Mark

Let the total work be W

The work completed by Ramesh = 110×W

The work completed by Ramesh's friend = 110×110000W

= 1100000×W

Ramesh's friend completes 1100000th of the work in the given time,