Case 1
Balance Sheet as on March 31, 2016 |
|||
Liabilities |
Amount (Rs) |
Assets |
Amount (Rs) |
Capital Fund |
20,00,000 |
Pavilion Work-in-Progress |
6,00,000 |
|
|
|
|
Case 2
Balance Sheet as on March 31, 2016 |
||||
Liabilities |
Amount (Rs) |
Assets |
Amount (Rs) |
|
Pavilion Fund |
10,00,000 |
|
Pavilion Work-in-Progress |
6,00,000 |
Less: Expenditure on Construction of Pavilion |
(6,00,000) |
4,00,000 |
|
|
Capital Fund |
20,00,000 |
|
|
|
Add: Pavilion Work-in-Progress |
6,00,000 |
26,00,000 |
|
|
|
|
|
|
|
Case 3
Balance Sheet as on March 31, 2016 |
||||
Liabilities |
Amount (Rs) |
Assets |
Amount (Rs) |
|
Pavilion Fund |
10,00,000 |
|
|
|
Add: Donation |
5,00,000 |
|
Pavilion Work-in-Progress |
6,00,000 |
Less: Expenditure on Construction of Pavilion |
(6,00,000) |
9,00,000 |
|
|
Capital Fund |
20,00,000 |
|
|
|
Add: Pavilion Work-in-Progress |
6,00,000 |
26,00,000 |
|
|
|
|
|
|