wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

State the type of plan and state whether they are Single use or Standing plan:

a. A type of plan which serves as a controlling device as well. (budget)

b. A plan based on research and analysis and is concerned with physical and technical tasks. (Method)

Open in App
Solution

a. Budget - A type of plan which serves as a controlling device as well. A budget is a Single-used plan which is developed for a one time project or event.

b. Method - A plan based on research and analysis and is concerned with physical and technical tasks. Method is a Standing plan as it is used for activities which occur regularly over a period of time.

flag
Suggest Corrections
thumbs-up
8
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Regulation of Respiration
GEOGRAPHY
Watch in App
Join BYJU'S Learning Program
CrossIcon