Suhan can do a work in 15 days and Ankush in 20 days. If they work on it together for 4 days, then the fraction of the work that left is
A
815
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
725
No worries! Weāve got your back. Try BYJUāS free classes today!
C
615
No worries! Weāve got your back. Try BYJUāS free classes today!
Open in App
Solution
The correct option is A815 Suhan's one day work = 115 Ankush one day work = 120 (Suhan + Ankush) one day work = 115 + 120 = 760 (Suhan + Ankush) 4 day work = 760×4 = 715 Therefore, Remaining work = 1 - 715 = 815