Suhan can do a work in 15 days and Ankush in 20 days. If they work on it together for 4 days, then the fraction of the work that left is ______ (2 marks)
Open in App
Solution
Suhan's one day work = 115
Ankush one day work = 120
(Suhan + Ankush) one day work = 115 + 120 = 760
(1 mark)
(Suhan + Ankush) 4 day work = 760×4 = 715
Therefore, Remaining work = 1 - 715 = 815