Suppose A takes twice as much time as B and thrice as much time as C to complete a work. If all of them work together, they can finish the work in 2 days. How much time B and C working together to finish it?

Open in App
Solution

Let the work done by A be x
A takes twice as much as B Therefore B take half of what time A takes.
B=x2
A takes thrice as much as C Therefore C take one third of what time A takes.
C=x3
All have them finish the work in 2 days
1A+1B+1C=12

1x+2x+3x=12
6x=12 Cross multiply
x=12
B=x2=122=6

C=x3=123=4
If B and C work together
=1B+1C

=16+14

=2+312 (Take LCM)

=512

If B and C work togethere they will take 125 days

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon