Question
Suppose
B
is
60
%
more efficient than
A
. If
A
can finish a job in
15
days, how many days
B
needs to finish the same job?
Open in App
Solution
B
is
60
%
more efficient than
A
A
finishes a job in
15
days
So,
A
's one day work
=
1
15
∴
B
's one day work will be
1
15
+
60
%
of
1
15
=
1
15
+
60
×
1
15
×
1
100
=
1
15
+
1
25
=
8
75
So,
B
finishes the work in
75
8
=
9
3
8
days.
Hence,
B
can do the same work in
9
3
8
days.
Suggest Corrections
0
Similar questions
Q.
If 5 person can finish a job in 10 days then in how many days will 15 persons finish the same job?
Q.
Suppose
A
is twice as good a workman as
B
and together they can finish a job in
24
days. How many days
A
alone takes to finish the job?
Q.
A can do a certain job in
12
days. B is
60
%
more efficient then A. Find the number of days take by B to finish the job.
Q.
Suppose
A
and
B
together can do a job in
12
days, while
B
alone can finish it in
30
days. In how many days can
A
alone finish the work?
Q.
A
,
B
and
C
can finish a job working alone in
72
,
24
and
36
days respectively. In how many days they can finish the job if they worked together?
View More
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
Related Videos
Time and Work
MATHEMATICS
Watch in App
Explore more
Time and Work
Standard VII Mathematics
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
AI Tutor
Textbooks
Question Papers
Install app