Question

<!--td {border: 1px solid #ccc;}br {mso-data-placement:same-cell;}--> A small terrace at a football ground comprises 15 steps each of which is 50 m long and built of solid concrete.
Each step has a rise of 4/1m and a tread of 2/1m. Calculate the total volume of concrete required to build the terrace.

[Hint : Volume of concrete required to bulid the first step =14×12×50m3]


Open in App
Solution

As we can see from the given figure, the first step is is 1/2 m wide, 2nd step is 1 m wide and 3rd step is 3/2m wide.
Thus we can understand that the width of step by 1/2 m each time when height is 1/4 m. And also, given length of the steps is 50 m all the time. So, the width of steps forms a series AP in such a way that; 1/2,1,3/2,2,..........

Volume of steps = Volume of Cuboid
=Length×Breadth Height
Now,
Volume of concrete required to build the first step =14×1/2×50=25/4
Volume of concrete required to build the second step =14×1/×50=25/2
Volume of concrete required to build the second step =14×3/2/×50=75/2
Now, we can see the volumes of concrete required to build the steps, are in AP series;
25/4,25/2,75/2......
Thus, applying the AP series concept,
First term, a=25/4
Common difference, d=25/225/4=25/4
As we know, the sum of n terms is ;
Sn=n/2[2a+(n1)d]=15/2(2×25/4)+(15/21)25/4)
Upon solving, we get
Sn=15/2(100)
Sn750
Hence, the total volume of concrete required to build the terrace is 750m3.